Sample projects under construction or recently
completed:
TRANSIT
Regional Transit Authority
Nashville, TN
Track Rehabilitation: Install 20,500 crossties,
change 148,500 LF CWR rail, 297,500 LF of surfacing track, replace 15
turnouts, replace 40 road crossings, rehab 3 bridges
New Track Construction: 9,300 TF new track, 11 new turnouts, construct
5 new bridges.
Completion Date: August 2006
Prime Contractor
Maryland Mass Transit Administration
Baltimore, MD
New Track Construction 14,500 TF ballasted
track installation, 1,400 LF restraining rail, 625 TF road crossings,
install 1 crossing diamond, install 3 crossovers, install 1 double crossover,
install 7 turnouts and remove 12 existing turnouts.
Completion date: November 2004
Subcontractor
Metropolitan Atlanta Rapid Transit Authority
Atlanta, GA
New Track Construction 19,500 TF rail with
concrete ties and CWR, 32 turnouts, 2 double crossovers, 3rd Rail installation,
950 TF direct fixation track and site paving.
Completion Date: August 2004
Prime Contractor
Metropolitan Atlanta Rapid Transit Authority
Atlanta, GA
New Track Construction 4,000 TF concrete
ties and CWR, 6 turnouts, 3rd rail installation, signaling and train
control, site work.
Completion date: October 2001
Prime Contractor
Dallas Area Rapid Transit
Dallas, TX
New Track Construction 12,700 TF of mainline
Track on concrete ties and CWR, 1,118 LF restraining rail, 9 turnouts,
3 single crossovers and 1 diamond crossing.
Completion date: April 2004
Subcontractor
Denver Regional Transit District
Denver, CO
New Track Construction 20,000 TF yard Track
with concrete ties and CWR, 38 turnouts in yard, 2 mainline turnouts
and 2 single crossovers, 3,000 LF restraining rail, 3,500 TF of Direct
Fixation track in concrete aprons and on steel beams in the maintenance
building.
Completion Date: June 2004
Subcontractor
[Back to top]
NEW TRACK
CONSTRUCTION
Southern Electric
Marion, AR
New Track Construction Sizing & Rail Car
Maintenance Yard Gradework Clearing, Grubbing, Excavation, Fill, Drainage
and ROW fence 90 acres New track construction of 9 miles of CWR track,
24 turnouts and Concrete/Steel tie track construction thru Repair Building
Completion Date: June 2004
Prime Contractor
Capital Metro
Austin, TX
New Track construction with a Coupled in Motion
Rail Weighing System, 1,500 TF of track with steel crossties and 2 turnouts
with steel switchties, completed gradework on a 2 acre site, reconstructed
1 grade crossing, installed the weigh scale including foundations and
Control House.
Completion Date: October 2002
Prime Contractor
Amtrak
Lorton, VA
New mainline track construction of approximately
6,200 TF, shift and line 3,250 TF, install temporary wood bridge, Change
200 crossties and install 5 turnouts
Completion date: June 2000
Subcontractor
Nissan North America
Canton, MS
New Track Construction 64,500 TF ballasted
track with CWR, 5,100 TF road crossings, 27 turnouts in Yard and 2 mainline
turnouts, Site work and Paving.
Completion Date: April 2003
Prime Contractor
Fort Campbell
Hopkinsville, KY
New Track Construction 24,000 TF track construction, 5 turnouts, 39,600
TF track removal.
Completion date: November 2001
Subcontractor
[Back to top]
TRACK
REHABILITATION
Florida Central Railroad
Orlando, FL
Track Rehabilitation Replace 16 track miles
of jointed rail with CWR rail, replace 16,000 railroad crossties, replace
30 turnouts and surface 16 miles of track.
Estimated Completion Date: March 2007
Prime Contractor
Indiana Department of Transportation
Nobelsville, IN
Track Rehab Hoosier Heritage Port Authority
/ Indiana Transportation Museum Replaced 9,400 crossties over 22 miles,
surfaced 16.5 miles of track, rebuilt 5 road crossings, installed 6
each crossing signals and placed 6,000 NT of ballast from railcar.
Completion Date: October 2004
Prime Contractor
Madison Parish Port
Tallulah, LA
New Track Construction 2,900 TF new track,
3 turnouts
Track Rehab 10,100 TF rail change, 2,300 ties replaced, 4 turnouts
replaced, 14,000 TF subgrade lime and cement slurry injected, 2 road
crossings replaced.
Completion date: 2003
Prime Contractor
Capital Metro
Austin, TX
Track Rehab 48,000 TF mainline rail replaced
with 133# CWR and track surfaced, 3,000 NT ballast installed and 2 public
road crossings replaced.
Completion date: April 2002
Prime Contractor
Birdsong Peanut
Gorman, TX
Track Rehab 16,900 crossties and 350 switch
timbers replaced.
Completion date: 2002
Prime Contractor
Military Ocean Terminal
Southport, NC
Track Rehab 8,800 crossties replaced, 89,000
TF track surfacing, 7,700 TF rail replacement, 97,000 TF ultrasonic
rail testing, 160 bridge ties replaced
Completion Date: 2004
Subcontractor
[Back to top]